If the spec.mon.count is 5 or more, then create
mon pdbs with maxUnavailable count as 2. We can
afford to have more than 1 mons down while
draining the nodes in this case.
Signed-off-by: sp98 <sapillai@redhat.com>
This commit update the PodDisruptionBudget policy to use version v1
Updated to policy/v1 as policy/v1beta1 PodDisruptionBudget is deprecated in v1.21+
Closes: https://github.com/rook/rook/issues/7917
Signed-off-by: parth-gr <paarora@redhat.com>
With simultaneous node drains, a mon can go down while another mon is failing over. This results in two mons down and ceph become inaccessible. The commit makes maxUnavailable=0 while a mon is failing over and updates it back to maxUnavailable=1 after the failover. This update action is best effort. Any errors while updating the maxUnavailable mon pdb is only logged
Signed-off-by: Santosh Pillai <sapillai@redhat.com>
- Update mon PDB to use maxUnavailable=1 instead of minAvailable. The maxUnavailable will always be 1 irrespective of the number of mons in the cluster
- Move mon PDB reconcile logic from Disruption Controller to Cluster Controller
Signed-off-by: Santosh Pillai <sapillai@redhat.com>